Milestone M4b – Migration

This page explains activities connected to the migration in M4b.

As before, the migration in this milestone has two sub-activities: one full upload and one delta upload. The data quality requirements for M4b is the same as M4a, but more criteria will count in the metering then before.

Primarily, missing metering points will now count as errors in the category the field belongs to.

Full upload is set to Wednesday October 26th, while the delta upload will be on Wednesday November 30th.